The government of Pakistan is trying to add electricity generation of__________MW to national grid by 2017- 18

  • A. 10,000
  • B. 10,400
  • C. 10,800
  • D. 11,200

Explanation

The government’s target was to add about 10,400 MW of electricity-generation capacity to the national grid by 2017-18. This was part of the plan to reduce Pakistan’s electricity shortfall.