Mohamand Dam which is being constructed on swat river will completed at the cost of Rs.________billion by 2024?

Correct answer: C. Rs. 183 billion

  • A. Rs. 143 billion
  • B. Rs. 163 billion
  • C. Rs. 183 billion
  • D. None of these

Explanation

The initial estimated cost of Mohmand Dam was about Rs183 billion, with completion targeted for 2024 in the plans reported at the time. The project is built on the Swat River in Khyber Pakhtunkhwa.